AIA G702 and G703: a plain-English guide for cost-plus builders

    ยท Bond

    AIA G702 and G703: a plain-English guide for cost-plus builders

    What the G702 and G703 are, how the numbers fit together, and how cost-plus builders use them to bill owners each month.

    If you bill owners monthly, you've probably filled in an AIA G702 and G703, or a spreadsheet that copies them. They're the standard forms for an application for payment (AFP) on a construction job. Here's what each one does and how the numbers connect.

    The G702: the summary page

    The G702 is the one-page application. It answers one question: how much is due this month? It starts from the original contract sum, adds approved change orders, and works down to the current payment due:

    LineWhat it means
    Original contract sumThe agreed price, or the budget on a cost-plus job
    Net change by change ordersApproved changes added or deducted
    Contract sum to dateThe two lines above, added together
    Total completed and stored to dateEverything earned so far, from the G703
    RetainageThe share held back until the end of the job
    Less previous paymentsWhat's already been paid
    Current payment dueWhat the owner pays this month

    The G703: the detail behind it

    The G703, the continuation sheet, is the schedule of values. Every line is a piece of the job, usually by cost code or trade, with its scheduled value, what was completed in earlier periods, what was completed this period, materials stored, the percentage complete and the balance left to finish. The G703's totals feed the G702.

    How cost-plus jobs differ

    On a fixed-price job, each line is billed by percentage complete. On a cost-plus job, you bill the actual costs incurred, plus your fee and any agreed markups, so the backup matters as much as the form: every receipt, supplier invoice and subcontractor bill behind each line, stamped with its cost code. Owners and their family offices often check that backup line by line.

    Where the time goes

    The forms themselves are quick. The time goes into everything around them: collecting receipts from the field, coding every invoice to the right job and line, chasing subs for their bills and lien waivers, and assembling the backup in the right order. That's usually one or two weeks a month for someone in the office.

    Three habits that make the monthly bill easier

    1. Code costs as they arrive, not at month-end.
    2. Keep the schedule of values and the budget on the same cost codes, so every bill has an obvious line.
    3. Collect the lien waiver with each payment, so the backup is complete before the bill goes out.

    This guide is general information, not legal or accounting advice. Check your contract and your state's requirements.